An internal audit has shown that problems that led to a massive overspend on the Fletton Parkway improvement scheme couldn’t have been anticipated.

Peterborough City Council was forced to pay an additional 3 point 6 million pounds towards the project.

It was hit by soil contamination, the presence of Great Crested Newts and a decision to upgrade lighting.